Cleanroom Humidity Spike Case Study: Psychrometric Troubleshooting & Balancing

CED Case Study — Master HVAC Simulator & Dynamic Psychrometric Charts

Calibrated to As-Built Drawing Specs: AHU-6101 Off-Coil (14.0°C / 99% RH) → Fan Exit (~16.0°C / 89% RH) → Booster Coils 6102 & 6103

%
CHWS: CHWR:
1. Master HVAC Flow Schematic (CAD Architecture)
STAGE 1: CENTRAL MAKE-UP & DEEP DEHUMIDIFICATION SYSTEM 2: CLEANROOM AREA "C & D" (PREPARATION & WASHING) SYSTEM 3: CLEANROOM AREA "B" (ASEPTIC STERILE CORE) OUTDOOR AIR (OA-6101) 18,625 m³/h (Min) 39.0°C DB | 30.0% RH w = 13.15 g/kg Dew Point: 18.3°C AHU 02-AH-6101 COIL LOAD: 100% (269 kW Max) Act. Duty: 209.2 kW Condensate: 67.7 kg/h OFF COOLING COIL (2A): 14.0°C DB | 99.0% RH w = 9.87 g/kg (CHW: 5/10°C) CHW Loop: 5.0 / 10.0 °C Fan + Filter F7 (+1.8 K Rise) Wi: Pre-heat 54kW + Steam 28kg/h LEAVING AHU 02-AH-6101 (2B) ~16.0°C DB | Su: 89.0% RH w = 9.87 g/kg | dp = 13.9°C (Wi: 16°C DB | 52% RH | w = 5.90 g/kg) System 1 General Area 9,280 m³/h @ 16°C COIL 02-E-6102 (50kW) In: 16.0°C | 89% RH STATUS: ON (CHW 5/10°C) Act. Duty: 36.1 kW Cond: 26.0 kg/h Out: 7.5°C | 99% RH COIL 02-E-6103 (38kW) In: 16.0°C | 89% RH STATUS: ON (DX Coil) Act. Duty: 21.8 kW Cond: 15.8 kg/h Out: 6.0°C | 99% RH (Includes 1,640 m³/h to 02-8-6101) FRESH AIR FEED (3) 6,170 m³/h (Min) 7.5°C | 99% RH w = 6.36 g/kg AHU 02-AH-6102 Mix (4): 17.0°C DB Reheat to 22.0°C Reheat: 32.0 kW (No Cooling Coil) SUPPLY TRUNK (5) 19,400 m³/h @ 22.0°C RH: 43.1% w = 7.08 g/kg Dew Point: 8.9°C ZONE TRIM COOLER CC-6201 to CC-6205 Sensible Re-cooling Trim: 18.0°C DB Δw = 0 (Dry Coil) CLEANROOMS AREA "C & D" (6) (13 Rooms Consolidated Box) Room DB: 21.5°C RH: 46.5% w = 7.41 g/kg COMPLIANT (≤55%) Internal Latent: +7.8 kg/h RECIRCULATED RETURN AIR (RA) 13,230 m³/h (68.2%) 21.5°C | 46.5% RH | w = 7.41 g/kg FRESH AIR FEED (3) 1,535 m³/h (Min) 6.0°C | 99% RH w = 5.73 g/kg AHU 02-AH-6103 Mix (4): 19.4°C DB Trim Heat to 20.0°C Reheat: 7.2 kW (No Cooling Coil) SUPPLY TRUNK (5) 33,520 m³/h @ 20.0°C RH: 44.9% w = 6.51 g/kg Dew Point: 7.7°C ZONE TRIM COOLER CC-6301 to CC-6305 Sensible Re-cooling Trim: 16.0°C DB Δw = 0 (Dry Coil) CLEANROOMS AREA "B" (6) (11 Sterile Rooms + Grade A LAF) Room DB: 20.0°C RH: 45.2% w = 6.55 g/kg COMPLIANT (≤50%) Internal Latent: +1.5 kg/h RECIRCULATED RETURN AIR (RA) 31,985 m³/h (95.4%) 20.0°C | 45.2% RH | w = 6.55 g/kg
2. Live 7-Point Psychrometric Process Charts (Dynamic State Labels)

System 2 Process: OA → 6101 Coil → 6101 Exit → Booster 6102 → Area "C & D"

COMPLIANT
State Point (Live Condition) Tdb (°C) w (g/kg) RH (%) Dew Pt (°C)

System 3 Process: OA → 6101 Coil → 6101 Exit → Booster 6103 → Area "B"

COMPLIANT
State Point (Live Condition) Tdb (°C) w (g/kg) RH (%) Dew Pt (°C)
3. Hydronic & Thermal Balance Summary

Central Hydronic Performance (AHU-6101)

Area C&D Cleanroom Impact (AHU-6102)

Area B Sterile Core Impact (AHU-6103)

HVAC Failure Investigation Sterile Cleanrooms Psychrometric Root Cause

A Real HVAC Failure: Production Humidity Hit 80% at 20°C — Why "Cold Air" Fooled the Facility Team

Published on CED Engineering & Facility Management (ced-engineering.com)

Walking into an established pharmaceutical manufacturing facility that has operated reliably for years, only to find the sterile production suite sitting at 80% RH instead of its design limit of 50% RH at 20°C, is a high-stakes scenario.

In critical environments, the default reaction when cooling equipment appears overwhelmed is often commercial and reactionary: "The thermal loads have grown; we need a larger chiller, an additional cooling stage, or a multimillion-dollar desiccant system."

When entering an existing plant without full visibility into undocumented site modifications, guessing is costly. The correct engineering response is systematic verification: coupling physical field audits with rigorous thermodynamic modeling.

The Physical Reality vs. The Sensor Readout

The primary Fresh Air Handling Unit (FAHU) was discharging air at 16°C dry-bulb. To the maintenance team, that reading confirmed the unit was cooling properly. However, temperature measures sensible energy alone—it says nothing about moisture extraction.

The Investigation: Two Root Causes

1. Throttled Balance Valve on the Primary Fresh Air Coil (Sensible Cooling Without Latent Removal)

During a previous winter operating period, maintenance had manually throttled the chilled water balance valve serving the primary make-up coil to divert flow to other building headers. That field change was never reverted.

When extreme summer outdoor ambient conditions arrived (39°C dry-bulb with high moisture content), the choked chilled water flow caused the coil surface temperature to rise above the air stream's dew point across most of its tube passes. The coil provided pure sensible cooling without condensing moisture. The air left the unit cold to the touch, but carried a high absolute moisture content (w > 11.5 g/kg) directly into the downstream system.

2. Maintenance Deficiencies on Secondary Sub-Cooling Booster Coils

In a decoupled cleanroom architecture, secondary booster coils are charged with deep sub-cooling to strip out residual moisture before make-up air mixes with recirculated room air. Due to neglected maintenance, these booster stages could not compensate for the elevated humidity coming off the primary unit. The untrapped latent load passed straight through into the production cleanroom.

The Resolution: Zero Capital Expenditure

By validating the failure mechanism in a psychrometric balance model rather than blindly purchasing new equipment:

  • The chilled water balancing valve on the primary FAHU was restored to its rated hydronic flow rate.
  • Surface fouling and operational parameters on the secondary booster coils were serviced and restored.
  • Cleanroom room humidity returned to its validated operating baseline (45% to 50% RH at 20°C) without procuring a single new piece of machinery.

Simulate This Exact Failure Mechanism Live

Test the thermodynamic impact of throttling the primary cooling coil from 100% to 50% and observe the real-time shift across 7 process points on live ASHRAE psychrometric charts.
See simulator in the begining of the page

Next
Next

when covering condenser with large plastic bag Is the solution